Guidance

PPN 10/23: Taking account of a bidder’s approach to payment in the procurement of major contracts

This PPN sets out how payment approaches can be taken into account in the procurement of major government contracts. It replaces PPN 08/21 from 1 April 2024

Update history

2025-04-24 12:00
Updated the document: Guidance on how to take account of a bidder’s approach to payment in the procurement of major contracts November 2023

2023-11-23 10:00
First published.