Local Environmental Management Plans for HS2 Phase One
These plans set out the site-specific control measures for HS2 contractors working within local authorities along the Phase One route.
Documents
Details
High Speed Two (HS2) Ltd and its consultant have produced Local Environmental Management Plans (LEMPs), a requirement under the Code of Construction Practice (CoCP). These plans are specific to each local authority area along the Phase One route. The LEMPs are based on environmental information currently available to the project, as reported within the Environmental Statement (including Supplementary and Additional Provision Environmental Statements).
The contractors working for HS2 Ltd will be required to comply with the LEMPs during construction works and must meet the High Speed Rail (London to West Midlands) Environmental Minimum Requirements (EMRs). The EMRs set out high-level environmental and sustainability commitments to be carried out during the planning and implementation of works along the Phase One route. The CoCP forms part of the EMRs.
Are the LEMPs finalised?
HS2 Ltd has been consulting with local authorities during the production of the LEMPs. The most up to date version of the LEMPs are published on this page. If, up to and during detailed design, new environmental baseline information comes to light (such as the identification of new sensitive receptors), then the LEMPs will be updated to reflect these changes.
What happens next?
Engagement events will be carried out to introduce and brief communities on local environmental information, management and mitigation. If local communities have comments relevant to the content of the LEMPs, they will be reviewed and updated, as required.
Updates to this page
Last updated 23 October 2024 + show all updates
-
Lichfield District Council Local Environmental Management Plan - file attachment updated
-
North Warwickshire Borough Council Local Environmental Management Plan - file attachment updated
-
Updated Buckinghamshire LEMP
-
Updated London Borough of Hammersmith and Fulham Local Environmental Management Plan.
-
Updated Brent, Camden, Ealing, Hillingdon, Kensington and Chelsea and City of Westminster.
-
Updated Stratford-on-Avon, Cherwell and West Northamptonshire and added Buckinghamshire whilst removing Aylesbury, Chiltern and Wycombe and Three Rivers and South Bucks.
-
Local Environmental Management Plans updated for: Brent, Camden, Ealing, Hillingdon, Kensington & Chelsea, and Westminster
-
4 x LEMPs updated with revised KESWMPs: Aylesbury, Chilterns, South Northamptonshire, Three Rivers.
-
London Boroughs plans updated
-
All LEMPs updated
-
First published.