Change description : 2025-12-10 09:00:00: New regulations are expected to come into effect in early 2026 to extend the commissioning window of the Green Gas Support Scheme (GGSS) to 31 March 2030. Subject to parliamentary scrutiny, applicants have an additional two-years to commission plants and begin injecting biomethane into the gas grid. [Guidance and regulation]
New regulations are expected to come into effect in early 2026 to extend the commissioning deadline of the Green Gas Support Scheme (GGSS) from 31 March 2028 to 31 March 2030. While this extension will be subject to the standard parliamentary scrutiny, the aim is to provide new applicants with an additional two years to commission plants, begin injecting biomethane into the gas grid and make their stage 3 application for GGSS registration. The proposed extension aims to maximise deployment and the associated carbon savings that can be achieved through the scheme.
The deadline for submitting new stage 1 applications will remain 31 March 2028. Under the current regulations the standard tariff lifetime is 15 years but if participants commission beyond 31 March 2028, their tariff length will not be extended and will end by 31 March 2043. For example, if an applicant has a commissioning date of 31 March 2030 (the final date possible under the extension), they would receive a tariff lifetime of 13 years.
Applicants who applied before 10 December 2025 will need to retain their original commissioning date. If this is not achievable, they may choose to withdraw and submit a new application. Please note that re-entry will be subject to the scheme’s eligibility criteria and conditions at the time of reapplication and is not guaranteed.
Applicants who submit stage 1 applications on or after 10 December 2025, but before the proposed regulations come into effect, must apply with a commissioning date no later than 31 March 2028. If the commissioning deadline becomes unachievable for an applicant in this category after the proposed regulations come into force, the date may be revised to a later date (no later than 31 March 2030) without the applicant needing to withdraw or reapply, provided they meet the necessary requirements under the regulations.
We will not publish a Call for Evidence for the 2025 Annual Tariff Review (ATR). The Review will be informed by the 2025 Biomethane Cost Survey, plus wider market intelligence and evidence gathered through regular stakeholder engagement.
20 December 2024
Added GGSS budget caps, production factors, and inflation forecasts for 2025-2026.
30 August 2024
The degression thresholds in the Budget Management guidance have been amended to reflect the new GGSS closure date of 31 March 2028.
4 June 2024
New regulations on the Green Gas Support Scheme which come into effect today (4 June) extend the scheme to 31 March 2028 (previously 30 November 2025).
22 December 2023
We have published new GGSS budget caps, production factors and inflation forecast effective from 1 April 2024, and made updates to the GGSS budget management guidance.
20 December 2022
We have published new GGSS budget caps, production factors and inflation forecast effective from 1 April 2023, and made updates to the GGSS budget management guidance.
20 July 2022
Budget caps (Table 4) and inflation forecasts (Table 3) have been extended to cover scheme financial years 2026/2027 and 2027/2028, following a regulatory amendment (Statutory Instrument 2022 No.592) which took effect on 1 July 2020.
27 April 2022
We have improved the explanation of GGSS budget management mechanisms, and added links to the new Green Gas Support Scheme (GGSS): expenditure forecast statements and tariff change notices page (https://www.gov.uk/government/publications/green-gas-support-scheme-ggss-expenditure-forecast-statements-and-tariff-change-notices).
6 December 2021
Inflation estimate for financial year 2025 / 2026 added to table 3.