Guidance

The 2020 EIA Regulations

The 2020 EIA Regulations

From 1st January 2021

Environmental Impact Assessments (EIA)

Projects listed in Schedule 1 of the 2020 EIA Regulations are subject to an EIA process as required by regulation 5(1). Projects listed in Schedule 2 are subject to a screening process to determine if an EIA is necessary, but the developer may wish to undertake an EIA as set out in regulation 5(2)(b), if they choose. To access further information on projects which are subject to the EIA process, please use the relevant link below.

Environmental Impact Assessments (EIA) - Transitional Cases

For projects where the Oil and Gas Authority decision on whether to grant consent is pending at the time when the 2020 EIA Regulations came into force, EIA’s are subject to the provisions of regulation 29 (Transitional and Saving Provisions relating to the 1999 Regulations). To access further information on EIA projects which are subject to the provisions of regulation 29, please use the relevant link below.

Screening Directions

Projects listed in Schedule 2 of the 2020 EIA Regulations require a screening direction in accordance with regulation 5(2)(a) to determine if an EIA is necessary. Screening directions for projects which have been through the screening process since 1st January 2021 can be accessed using the link below.

Deep Drilling Screening Directions

Pipeline Screening Directions

Production Screening Directions

Regulation 5(3) Decisions that No environmental impact assessment is needed without a screening direction

Schedule 3 Projects

The 2020 EIA Regulations provide that projects that fall under Schedule 3 do not require an EIA where the Secretary of State considers that the project is not likely to have a significant effect on the environment pursuant to regulation 7. Those projects are:

  • The construction of a pipeline for the transport of oil, combustible gas, or chemicals, or for the transport of carbon dioxide streams for the purposes of geological storage of carbon dioxide, or the maintenance, repair, replacement, protection or extension of an existing pipeline constructed for those purposes where no part of the pipeline or related works would extend more than 500 metres from a well or any part of an installation to which that pipeline would be directly or indirectly attached.

A list of Schedule 3 project decisions made since 1st January 2021 can be accessed at the following link:

Published 5 January 2021
Last updated 2430 October 2023 + show all updates
  1. Update Schedule 3

  2. Schedule 3 Projects Register updated

  3. Schedule 3 Spreadsheet updated

  4. Schedule 3 Projects Register updated to most recent version

  5. Link added to EIA Submissions and Decisions - 2023 webpage

  6. Schedule 3 Projects Register updated to most recent version

  7. Schedule 3 Projects Register updated to most recent version

  8. Schedule 3 project register - updated

  9. Schedule 3 Projects register updated

  10. Schedule 3 Projects Register - file attachment UPDATED

  11. Schedule 3 Projects Register weekly update

  12. Schedule 3 Projects Register updated to most recent version

  13. Schedule 3 Projects register - weekly update

  14. Schedule 3 updated

  15. Schedule 3 spreadsheet updated

  16. Schedule 3 Projects register updated to most recent version

  17. Updated Schedule 3 Projects Register - 03/07/2023

  18. Schedule 3 Projects Register w.c. 26.06.2023 - updated

  19. Schedule 3 spreadsheet updated

  20. Schedule 3 Projects Register updated to most recent version

  21. Schedule 3 Project Register updated to most recent version

  22. Schedule 3 Projects Register - 29.05.2023 - UPDATE

  23. Current Schedule 3 Spreadsheet

  24. Schedule 3 Projects Register updated to most recent version

  25. Updated Schedule 3

  26. Schedule 3 Project Register updated to latest version

  27. add 2023 Pipeline Screening Directions link

  28. Schedule 3 projects register update

  29. Schedule 3 Projects Register updated

  30. Link added to Deep Drilling Screening Directions - 2023

  31. Schedule 3 Projects Register updated to most recent version

  32. Schedule 3 spreadsheet updated

  33. Schedule 3 Project Register updated.

  34. Most recent Schedule 3 projects register uploaded

  35. Schedule 3 register updated

  36. Updated Schedule 3 Projects Register added

  37. Updated Schedule 3 spreadsheet

  38. Schedule 3 Projects Register Updated

  39. Update to schedule 3 projects register

  40. Updated Schedule 3 Projects Register as at 22.08.2022

  41. Schedule 3 uploaded

  42. Schedule 3 Projects Register updated

  43. Schedule 3 register updated

  44. Schedule 3 Projects Register w.c. 18.07.2022 - Update

  45. Schedule 3 projects register updated

  46. Schedule 3 updated

  47. Schedule 3 updated

  48. Schedule 3 spreadsheet updated

  49. Schedule 3 register updated

  50. Schedule 3 updated

  51. Schedule 3 Projects Register updated to most recent version

  52. A link to 2022 Environmental Statements added.

  53. Schedule 3 updated

  54. Schedule 3 updated

  55. Schedule 3 register updated

  56. Schedule 3 replaced with the newest version

  57. Schedule 3 Register updated

  58. Schedule 3 Register updated

  59. Schedule 3 project register updated

  60. Update to Schedule 3 Projects Register

  61. Updated schedule 3 spreadsheet

  62. Addition of Pipeline Screening Directions - 2022

  63. Schedule 3 register updated

  64. Addition of link to Production Screening Direction 2022 page

  65. Weekly Schedule 3 Projects Register update

  66. Weekly Schedule 3 Projects Register Spreadsheet Update

  67. Weekly Update to Schedule 3 Projects Register

  68. Addition of Deep Drilling Screening Directions page for 2022

  69. Schedule 3 Project Tracker updated

  70. Schedule 3 tracking sheet updated.

  71. Schedule 3 tracking spreadsheet updated

  72. Schedule 3 register updated

  73. Schedule 3 tracker updated.

  74. Schedule 3 Projects Register updated.

  75. Weekly Schedule 3 Projects Register Spreadsheet

  76. Updated Schedule 3 register

  77. Schedule 3 tracking register updated.

  78. New schedule 3 register uploaded

  79. Schedule 3 Projects Register updated.

  80. Updated Schedule 3 register

  81. Updated Schedule 3 Projects Register,

  82. Schedule 3 Register updated

  83. updated schedule 3 register

  84. Weekly Schedule 3 Projects Register udpate

  85. Updated schedule 3 register

  86. Updated Schedule 3 Register

  87. Schedule 3 Projects Register weekly update

  88. Weekly Schedule 3 Projects Register update

  89. Schedule 3 projects register updated.

  90. Schedule 3 register updated

  91. Updated Schedule 3 Register

  92. Schedule 3 tracking spreadsheet updated.

  93. Updated Schedule 3 Register

  94. Schedule 3 tracker updated.

  95. Schedule 3 tracker updated.

  96. Schedule 3 register updated.

  97. Weekly 'Schedule 3 Projects Register' update

  98. Schedule 3 Register updated

  99. Schedule 3 tracking sheet updated.

  100. Schedule 3 Projects Register updated.

  101. Weekly Update to Schedule 3 Projects Register Spreadsheet

  102. Schedule 3 tracking updated.

  103. Schedule 3 tracking spreadsheet updated.

  104. Schedule 3 tracking spreadsheet updated.

  105. Update to Schedule 3 Projects Register

  106. Schedule 3 Projects Register updated.

  107. Addition of section for 'Environmental Impact Asssements (EIA) - Transitional Cases' within the 'Environmental Impact Assesssments (EIA)' section

  108. Weekly update to the Schedule 3 Projects spreadsheet

  109. Update of - Sched 3 spreadsheets - 25/01/2021

  110. 'Schedule 3 Projects Register' spreadsheet weekly update

  111. First published.